Case Studies

An efficient emergency cooling solution ensured the chemical manufacturing process

Written by Coolworld Rentals | Oct 13, 2026, 7:02:23 PM

A malfunctioning refrigeration system, including a plate heat exchanger, threatened a chemical manufacturing process. The production process required brine at -12 °C. Coolworld provided a suitable rental refrigeration solution on short notice.

How was Coolworld able to help the pharmaceutical customer?

  • Ensuring a temperature-critical process at -12 °C
  • Rapid deployment and commissioning within approximately 4 business days
  • Installation of two high-performance chillers, including a buffer tank and a plate heat exchanger
  • Close coordination with the client and partner to ensure a smooth implementation
Wondering why the pharmaceutical customer was so satisfied with Coolworld’s assistance? Then please read on.