In the heart of downtown Geneva, an existing cooling system had to be dismantled. A property management company needed a temporary solution to maintain water temperatures—without disrupting building operations.
How was Coolworld able to help the property management company?
- Cooling and heating were ensured during the renovation phase.
- Installation of a chiller, boiler, and oil tank in the city center.
- Flexible rental period of 85 weeks—with an option to extend.
- Precise temperature control set to +7 degrees (cooling) and +75 degrees (heating).
Everything at a glance
During the dismantling of an old refrigeration system, the building remained fully operational thanks to a temporary complete solution. Coolworld installed a chiller, a boiler, and a 6,000-litre oil tank, with precise temperature settings of +7°C and +75°C. This ensured uninterrupted climate control despite the major construction work.
-
Modernization in the heart of Geneva
A property management company modernized the building’s central cooling system in the heart of Geneva.
-
No compromises on comfort
Despite the construction work, occupants of the property were able to continue enjoying air-conditioned spaces thanks to the temporary solution.
-
Technically sophisticated complete solution
Coolworld provided a 500 kW chiller, a 600 kW boiler, and a 6,000-litre oil tank.
-
Flexible rental period, full control
85-week rental period with a flexible extension option, including precise temperature control for both cooling and heating.