Temporary Cooling for Server Room During Renovation

A cooling and air-conditioning specialist company from NRW needed temporary server room cooling during switchover works in an office building. The existing air-conditioning had to be shut down – Coolworld ensured reliable cooling. 
 
 
How did Coolworld help the specialist company?
  • Indoor installation of a 50 kW climate cabinet and outdoor 100 kW chiller 
  • Constant +16 °C maintained in the server room 
  • Installation in half a day – solution implemented within 1 week
You can find out more below.

All the information at a glance

During the switchover works, a server room in an office building in NRW needed to be temporarily cooled. Coolworld supplied a 100 kW chiller and a 50 kW climate cabinet. Thanks to the customer’s own installation and the strong support from our cooling experts, the solution was up and running in just half a day.

Cooling for data centers

A specialist company focusing on the cooling of server rooms and data centers – with a focus on operational reliability.

Cooling during system switchover

During the renovation, a temporary solution was needed to prevent downtime in the server room.

Efficient equipment in use

Coolworld supplied a 100 kW chiller for outdoor use and a 50 kW climate cabinet for indoor use – temperature consistently at +16 °C.

Perfect collaboration on site

The customer carried out the installation themselves, supported by Coolworld experts Emre Tasdögen and Olaf Hansen – implemented hand in hand.